# Installation

### Flush Mount Drive Connection

* Install your 3 Gang Box on or inside your wall

  <figure><img src="https://3040525219-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2F-MhFI6SSKpm8M7EkrYqp%2Fuploads%2Fgit-blob-79fc98a153c7e68bf21215b96b33a138a6b74969%2F3%20Gang%20Box.jpg?alt=media" alt=""><figcaption><p>Standard 3 Gang Electrical Box</p></figcaption></figure>
* Install conduit between the Showstopper Base and network switch
* Run Showstopper Cable and Cat5 Cable through conduit
* Wire your cables into the back of the Drive Connection
* Attach the green ground wire from the faceplate to the gang box
* Attach the face plate to the gang box and begin using your Drive Connection!

### Surface Mount Drive Connection

* Remove the face plate from the back enclosure

<figure><img src="https://3040525219-files.gitbook.io/~/files/v0/b/gitbook-x-prod.appspot.com/o/spaces%2F-MhFI6SSKpm8M7EkrYqp%2Fuploads%2Fgit-blob-157670089b085d3c61b2ba92a7bb3e6a9d95c2c1%2Fimage.png?alt=media" alt=""><figcaption><p>CCI Surface Mount Enclosure</p></figcaption></figure>

* Install the box on the wall. Be sure to use appropriate wall anchors
* Install conduit between the Showstopper Base and network switch
* Run Showstopper Cable and Cat5 Cable through conduit
* Wire your cables into the back of the Drive Connection
* Attach the green ground wire from the faceplate to the gang box
* Attach the face plate to the gang box and begin using your Drive Connection!